United States - Z1DA--631-23-016 Abate Asbestos Renovation 2024

For more information and to make a bid you will need to go to the third party website.

Details

Provided by Open Opps
Opportunity closing date
06 November 2024
Opportunity publication date
24 October 2024
Value of contract
to be confirmed
Your guide to exporting
Report opportunity

Description

View Changes 631-23-016 Abate Asbestos Renovation 2024
Site Visit Questions and Answers

Q1: Does the VA have a certain sequence for the rooms or are we able to schedule rooms in an order which is most efficient?
A1: There is no ordered sequence, however, the VA to have 35 calendar days notice prior to start detailing specific room start dates and finishes. Coordinate with COR.

Room 2109 MUST be completely abated during off hours, and over a weekend. Starting FRIDAY 1630 MONDAY 0630. All areas are to be abated off hours. Re-finishing can occur during business hours. Sequencing of room abatement and refinish to be kept to absolute minimum in order for VA to return these spaces to use.

Q2: Will the VAIH be able to get TEM results within <12 hours to allow an area to be abated one night and the containment removed the next?
A2: Typical wait time for TEM results is 24hrs. This will depend on time of day delivered to lab and day of week. VA not planning on expediting TEMs.

Q3: Is the CPIH required to be onsite during the VAIHs clearance collection and during containment removal activities?
A3: Yes, CPIH is required to be onsite during all abatement activities see Specification Section 2.2 for the scope of the CPIH. The CPIH is also expected to accompany the VPIH on all visual clearance inspections.

Q4: Can B044 and B046 be done together at one time?
A4: B044 and B046 can both be completed at the same time. However, the VA planned this to be done as separate containments and would need to be abated that way but can be done at same time. However, VA to have 35 calendar days notice prior to start detailing specific room start dates and finishes. Coordinate with COR.

Q5: At B12 Room 7, the door will need to remain open while awaiting the TEM results. Do you require plywood to be secured within the opening for security purposes?
A5: The SOW was incorrect in Room Number see attachment B12 Room 004 but correct is Room 4 the landing and room connected to the stairwell. There are three doors so it is expected that the outer door will be able to remain closed during abatement. Decon can go in Room B2 and window opens in B3 and can be used for negative air. Window unit will need to be removed (or moved) potentially so GC to include.

Q6: There is no vent location in 2109.  Since this room requires TEM sampling, the containment will have to remain up for at least one daytime shift while the hospital is under operation.  Can we vent through 2108?  Keep in mind this will require HEPA exhaust tubing to be suspended from the ceiling until the containment is removed. 
A6: Reference attachment Ventilation in Room 2109 . Depending on when construction starts there are 3x windows that can be used for ventilation, rooms 2129, 2150, and 2152. VA to have 35 calendar days notice prior to start detailing specific room starts and finishes. Room 2109 MUST be completely abated during off hours, over a weekend. Starting FRIDAY 1630 MONDAY 0630. Coordinate with COR.

GC will have to remove the whole window unit if they want to use window in room 2108.

Q7: Can you please provide the sign in sheet from the site walk?
A7: Yes, the sign in sheet is attached.

Q8: Is the base to be installed vinyl or carpet?  And it all appeared to be 6", is that correct?
A8: Johnsonite 6 height Color: Snow White or equivalent. Supersedes 4 that is in the spec.

Q9: Waiting Room 2109 - Where is the closest exhaust/ventilation opening to route negative air?
A9: See answer to Q6.

Q10: Rooms 1072,1299,1293,2109 - Please confirm that there is tile and mastic under the carpet in these rooms.
A10: Based on previous adjacent abatement and homogeneous finish, the above rooms are presumed to have mastic and leveler that need to be abated.

Q11: Is the VA carrying a VPM for this off-hour project?
A11: The VA is providing a VPIH, the Contractor is responsible for a CPIH. VA will be using Mabbett and Associates Inc for VPIH services.

Q12: Who is responsible for paying for the TEM? 
A12: VA is paying for the first TEM, contractor is responsible for subsequent TEMs if the first test fails.

Q13: Will every room be available during the entire project, or will they be completed in phases?
A13: There is no ordered sequence, however, the VA to have 35 calendar days notice prior to start - detailing specific room start dates and finishes. The ability to do multiple spaces will depend on the contractor # of crews, means and methods, and ability to immediately start refinishing after abatement activity. Coordinate with COR.

Room 2109 MUST be completely abated during off hours, and over a weekend. Starting FRIDAY 1630 MONDAY 0630. All areas are to be abated off hours. Off Hours considered 1630-0630. Re-finishing can occur during business hours. Sequencing of room abatement and refinish to be kept to absolute minimum in order for VA to return these spaces to use.

Q14: Thermoset Rubber base is listed on the Specifications but no brand, color, or Height. Just straight base for carpet and cove for LVT. Most of the rooms have 6-inch base, should we figure for 6-inch base or 4-inch base?
A14: See Q8.

Q15: Is self-leveling required? 
A15: Yes see Spec 09 05 16.

Q16: B044 Carpet Tile is Shaw Veil Match Existing Color. What color is the Existing color?
A16: Product has been discontinued, replace with Structure 5T297 24 x 24

Q17: Who is responsible for moving furniture?
A17: VA will move furniture.

Q18: Is there a Wage Determination?
A18: The appropriate wage determination is MA20240003 10/11/2024. See Attached.

Q19: There is an Above Ceiling Work Permit attached in the solicitation, Does the VA anticipate work to be done above the ceiling?
A19: It is not anticipated but if there is any reason for above ceiling work due to means and methods it is there for awareness on procedure.

Q20: There is an electrical panel schedule attached to solicitation, does the VA anticipate Electrical work to be done?
A20: No there is no anticipated electrical scope for this project.

Q21: There is a Mechanical and plumbing system valve charts attached to the solicitation, Does the VA anticipate Mechanical and Plumbing work to be done?
A21: No there is no anticipated mechanical or plumbing scope for this project.

Q22: There is a hot work permit attached, does the VA anticipate hot work to be done?
A22: It is not anticipated but if there is any reason for above ceiling work due to means and methods it is there for awareness on procedure.

Q23: Shaw, Veil Carpet Tile, TME is this Shaw, Patcraft, S319V-Veiled?

A23: Product has been discontinued, replace with Structure 5T297 24 x 24

Q24: Are transitions required for the new to existing finishes? Please specify.

A24: Use Schluter Systems edge protector and profile trim. Select appropriate transition product between flooring. Use Satin Nickle Anodized Aluminum , provide samples with shop drawings.

Opportunity closing date
06 November 2024
Value of contract
to be confirmed

About the buyer

Address
241-NETWORK CONTRACT OFFICE 01 (36C241)

Bid for tender

If your company meets the requirements of the tender, go to the website where the tender is hosted and submit your bid.

This website contains links to other websites that we do not control or maintain. We are not responsible for the content of these sites. We provide these links for your convenience only, and do not necessarily endorse their content.

Before entering into a contract you need to apply for any necessary export licences, which can include applications to trade in certain goods. You should also make your own enquiries and be satisfied by the accuracy of any information supplied to you.

Go to third party website
Is there anything wrong with this page?