Germany - Extension of the Marburg district administration, EOR cabling data center

For more information and to make a bid you will need to go to the third party website.

Details

Provided by Open Opps
Opportunity closing date
18 February 2025
Opportunity publication date
15 January 2025
Value of contract
to be confirmed
Your guide to exporting
Report opportunity

Description

A new data center is being built as part of the extension. This LV includes its EOR cabling.
System description of the modular, migration-capable passive cabling system:
For this project, a scalable cabling system based on pre-assembled fiber optic and copper cables is to be offered, which guarantees a mixed use of migration-capable, modular copper and fiber optic modules that can be installed without tools within a 19" module rack.
The system offered must allow the installed cabling to be reused for future migrations.
The components used must positively support the airflow for cooling the data cabinets.
The cabling system must demonstrably have a positive influence on the GREEN-IT certification option due to the following properties:
- high energy saving potential, optimized cooling
- Conservation of resources
- Reuse of components
- recyclable products
In addition to all quality assurance measures, a 20-year manufacturer's system guarantee is required.
580 module supports and accessories .
110 pcs. Fiber optic connections 2 to 8x MPO/MTP 24 to 96 fibers
72 pcs. RJ 45 connections 10 to 15 m with 10 GbE modules
350 pcs. Fiber optic patch cables Duple LC 0.50 to 2.00 m

Opportunity closing date
18 February 2025
Value of contract
to be confirmed

About the buyer

Address
Landkreis Marburg-Biedenkopf

The deadline to apply for this opportunity has passed.
Visit the opportunities page to find another.

Is there anything wrong with this page?